Power plant in Tarakan Hampered

. Selasa, 12 Juli 2011

TARAKAN - PT Service Plan of the National Electricity (PLN) Tarakan to start work on development projects Steam Power (power plant) is in the middle of June Sungi Mayan Village North Tarakan Subdistrict Juwata Peramai experiencing constraints.

This is because there are still some residents that the protests have not received compensation for these lands. Still the problem is the Mayor of Tarakan Udin Hianggio request to the Regional Secretary (Secretary), Badrum with the team to quickly resolve this issue.

"I've asked the regional secretary promptly on this issue thoroughly. Sebabkita promised to PT PLN to support power plant development in the interests of society. So if you give half measures do not help," he said on Monday (7/11/2011) at his office .

Udin admitted, very disappointed with the work of his staff who can not cope with the problems of land compensation to the community. Because sepengetahuanya land restitution has been made by PT PLN.

"It was already facing PLN me that restitution of land to the community has done. Why now is there are people who are protesting do not get land compensation. There's something going," he said

Writer: Junisah
Editor: Adhinata Kusuma

Sources: kaltim.tribunnews.com (July 11, 2011)